The Councilor for Infrastructure, José Alberto Tomé, has reported that the procedure for the award of the stabilization works of the Burriana slope, first phase, has begun, after the approval of the file by the Local Government Board.
These works will be carried out between Felipe Street and the landscaped access from Capistrano, over a length of 150 meters.
The budget for the execution of this work amounts to 806,939.31, with an execution period of four months from the signing of the rethinking document and the financing is municipal.
The project contemplates the necessary actions for the stabilization of said slope, such as double-braided mesh protection, wiring, reinforcement with a cable network, placement of breakwaters, retaining wall, drainage, etc.
The project has all the favorable reports from the different municipal services